Edison Drive Reconstruction Project
This letter is to advise you that the Edison Drive Reconstruction Project is scheduled to begin on June 6, 2016 and the contractor will be Mark Anthony Construction.
The construction will take place in five stages:
Stage 1: Widening on west side – week of June 6
Stage 2: Construction on east side – Early June to mid July
Stage 3: Construction on west side – mid July to late August
Stage 4: Pour drives and curbs – early August to late August
Stage 5: Construction on Cul-de-Sac – late August to mid September
There will be days when truck delivery will not be possible. This will be coordinated to the best of our ability and with as much notice as possible for businesses to schedule accordingly.
The mail service will be altered by the construction due to mailboxes not being at the curb. there will be a temporary mailbox on-site for mail delivery.
Please remove any landscaping installed in the city right-of-way. During the removal and replacement of Edison Drive anything in the right-of-way will also be removed and discarded.
A Facebook group page has been created for this project. It can be found by typing Edison Street Reconstruction Roseville Michigan into the search bar on Facebook. This page has pdf’s of the construction stages and will provide updates on the construction schedule as well as pictures and videos throughout the project. Please request to join the group and you will be verified.
We thank you for your patience and cooperation during this project. If you have any questions please contact the City of Roseville Engineering Department at 586-445-5445.